JOHOR BARU, Aug 5 — After the same witness took the stand on Thursday on the second day of a court hearing involving Country Garden Danga Bay, ...
“All this is in the written submissions... Leonard Yeoh of Malaysian law firm Tay and Partners said that if each of the 30-odd witnesses were to individually go through their evidence in the same way, the trial could take up to 100 days to complete. Two hours later, the case was adjourned before Yeoh, the developer’s lawyer, could cross-examine him. The trial on Thursday began with DeCruz questioning Soh over the alleged discrepancies that he found between a sales contract, which he had originally signed when he bought his apartment in 2013, and a copy of the same contract that he had received from the developer’s lawyer. The trial resumed at 2pm on Thursday with Soh returning to the stand to elaborate on the documents that he had presented to the court. He was referring to the plaintiff’s examination of evidence that was submitted to the court.
Mr Leonard Yeoh of Malaysian law firm Tay and Partners said that if each of the 30-odd witnesses were to individually go through their evidence in the same way, ...
A view of the clubhouse area of Country Garden Danga Bay condominium complex in Johor Bahru, Malaysia. Mr Leonard Yeoh of Malaysian law firm Tay and Partners said that if each of the 30-odd witnesses were to individually go through their evidence in the same way, the trial could take up to 100 days to complete. 'It could take up to 100 days': Country Garden Danga Bay lawyer objects to slow progress of Malaysia court proceedings
JOHOR BAHRU: The trial for a class action lawsuit filed by condominium unit owners against developer Country Garden Danga Bay kicked off in the Johor Bahru ...
The report does not state this,” said the lawyer from Tay and Partners. Advertisement Advertisement
JOHOR BAHRU — Embattled Johor developer Country Garden Danga Bay has launched a fresh claim against five Singapore members of a condominium management ...
The Royal Strand and Lovell plot comprises some 1,500 apartments of the more than 9,000-unit development. Among those documents was a quantity surveyor report on his apartment. JOHOR BAHRU — Embattled Johor developer Country Garden Danga Bay, which is embroiled in a separate court case against dozens of property buyers from Singapore, China and Malaysia, has launched a fresh claim against five Singapore members of a condominium management committee over a recent change of property manager. The five members are part of the management committee for Royal Strand and Lovell, one of four plots of the luxury condominium development. JOHOR BAHRU — Embattled Johor developer Country Garden Danga Bay has launched a fresh claim against five Singapore members of a condominium management committee over a recent change of property manager. - Johor developer Country Garden Danga Bay has filed a claim against five members of its condominium management committee
TODAY understands that four are Singaporeans and one is a Singapore permanent resident. The case is set to be heard for the first time at the Johor Bahru Strata ...
During the meeting, the committee had voted in favour of changing its existing property manager Bright Property Services. The strata management tribunal is a legal body that moderates disputes related to buildings with a strata title. Country Garden Danga Bay developer files claim against Singapore members of condo committee over change in property manager
JOHOR BAHRU: The trial for a class action lawsuit filed by condominium unit owners against developer Country Garden Danga Bay in the Johor Bahru Civil High ...
“I don’t know why we are going through all these again since the witness statement has been submitted. The case was later postponed due to the COVID-19 pandemic. Advertisement This is a very clear sign that the pages were swapped out,” he said. Advertisement Advertisement